A Short Guide to Estimating Software Projects
Are you tired of:
- Coming in late and
over-budget on projects?
- Hearing the same excuses
over and over for why things didn't go as planned?
- Feeling as though lessons
were learned--but still ending up in the same boat on the next project?
If this sounds familiar, welcome to the club. It's a large club. If you no
longer want to be a member, there are things you can do that will help, some of
which I've written about on this website--but none is more important and
fundamental than starting with a good estimate.
A Bad Estimate Kills a Project Before it Starts
Is it possible to recover from a bad estimate? I've never seen it, at least
not when the estimate is significantly off. Let's face it: a bad estimate means
we underestimated. The risk of this is often downplayed at the
start of a project but becomes a crisis at the end of it, when it results in
the following "triple-whammy":
- The client or stakeholder is
angry because the project is not able to meet a deadline, is not as
polished as expected, or is a financial embarrassment;
- In a rush to complete the
project on time, the developers are forced to take shortcuts which
manifest as quality and maintenance issues;
- Future productivity is
slowed down because time is split attending to bugs and issues on the
previously rushed project.
This last point in particular is why some companies find high performance
so elusive. They seek to compel greater productivity by setting aggressive
targets (i.e. estimates), but it backfires and ends up dragging them down
instead.
To break out of the repeating cycle of bad estimates, we must be willing to
change our perspective and our approach to estimating.
Embracing the Reality of "Planning Fallacy"
Even when we think we won't underestimate, we do anyways.
This is not apparent to everyone, but this has been exhaustively
researched, in far ranging applications beyond software development. It doesn't
matter if you ask someone how long it takes to drive somewhere, build a house,
dig a hole, or write a letter. It's all been tested, and researchers have found
that humans have an inherent bias to underestimate, across the board. There is
even a scientific name for it: planning fallacy.
Not only is planning fallacy consistent across disciplines, a more
incredible finding is that we repeat it even when we know we
underestimated the last time. Who can explain this quirk of human
cognition? Not me, but all I--and you--need to know is that it is real, and it
exists. If there is any doubt, by all means, look it up;
this is the first step to becoming a better estimator. Everything from here on
out is about how to beat planning fallacy.
Quality is More Work Than We Expect
Quality refers to the fit and finish of our design and the usability of our
interface. It refers to the performance of our features and a lack of bugs. It
refers to the underlying architecture of our system, and its capacity to grow
and adapt to changing uses. It refers to the cleanliness of our code, and the
ease with which it can be maintained. It means many things.
Ensuring high quality requires a lot of extra time, work, and planning. On
the other hand, rushing to meet deadlines, and trimming out
"non-essential" work, is a good way to end up with low quality.
Planning fallacy and quality problems compound each other; first you didn't
estimate enough to get good quality, and then the project had to be held back
even further in order to address the quality problems. In such cases projects
don't end up just "a little" late and over-budget, but rather
dramatically late and over-budget. I've frequently seen these projects in the
"green" right up until the first quality problems start getting
discovered, at which point they suddenly go into the "red".
How Much Are You Willing to Invest in Better Estimating?
We need to estimate better, but the challenge is how to estimate adequately
given that the world is knocking down our door to do it quickly.
This results in throwing out off-the-cuff, overly optimistic
estimates--which come back later to haunt us. Let's take a moment now to pause
and break down the estimating process. There are those who think that spending
more time on estimates will not make them better, but I disagree. At a
certain point yes, but it's a simple truth that if you do a more careful
analysis you will almost always arrive at a better estimate.
It's not the only option, however. In fact, I offer you three options,
based on how much time and energy you have to invest in estimating:
- The quick and dirty method, when there really is no time to spare. It
has drawbacks, but it will at least give you a fighting chance if you
don't have time to go beyond it.
- The predictive method, when you're in a Waterfall situation and you
need to create an estimate that may end up as a "fixed" budget
or timeline. This requires more time and analysis, but I'll share
some tips for doing it well.
- The empirical method, which has the benefit of being both
relatively quick and accurate, but requires embracing an Agile way of
working.
I actually recommend reading each of these methods, because there are
shared principles, and they build on each other in certain ways.
A Preface: 5 Estimating Rules You Should Never Violate
Regardless of how you go about it, observing the following principles are
important for everyestimate:
1. Get Estimates from the Source. I've seen detailed estimates and project plans produced by project
managers who never once consulted anyone on the development team. This is an
excellent way to make bad assumptions and produce a bad estimate. Always get
the input and perspective of whoever is going to actually do the work. If
that's a team of people, get the team to participate in the estimate. Don't
take anything as the final estimate; there is still work ahead
to build and refine it, but this is the starting point.
2. Make Sure Everyone Really Understands the Requirements. Lazy requirements will result in a bad
estimate every time. This means making sure everyone understands the context
and intent behind the requirements, which is a matter of good communication. It
also means putting in the work necessary to make the requirements comprehensive
and detailed enough to estimate. The more room you leave for ambiguity or
misperception, the greater the odds of missing something big in the estimate.
3. Avoid Influencing the Estimate with "Weasel Words". There are many sneaky ways estimates are
manipulated. The following psychological appeals are very effective at
getting people to lowball their estimates :
- "This should't take
more than a couple of days, right?"
- "Really? I didn't think
this was going to take you that long."
- "Remember that we
really need this estimate to come in under $50,000."
- "My guess is that this
estimate will come in at about 100 hours, but let me know what you come up
with."
- "You should be able to
do this a lot faster this time."
I've used a mix of tactics above; some are designed to elicit an emotional
reaction, like fear, self-doubt, or embarrassment; others are cognitive tricks
such as the use of anchoring and priming. For the sake of simplicity I refer to
them as "weasel words" because they are great at weaseling in the
agenda of lower estimates, under the radar.
If you seek rational, realistic estimates, you must guard against using
such language, consciously or subconsciously. To understand in depth how the
estimating process is influenced by such tactics, a good read is the book Thinking, Fast and Slow by Daniel Kahneman (who
incidentally was one of the pioneering researchers of planning fallacy).
4. Guard against "Groupthink" and the "Halo effect".
"Groupthink" is a phenomena where group conformity takes precedence over independent thinking, and can happen when conflicts or alternative ideas are frowned upon or received poorly.
"Groupthink" is a phenomena where group conformity takes precedence over independent thinking, and can happen when conflicts or alternative ideas are frowned upon or received poorly.
This is the opposite of what we need to estimate well, because only by
challenging and questioning each other are we likely to "shake out"
the bad assumptions and missing analyses that are the source of our planning
fallacy. A related phenomena is the "halo effect", which is the
effect of not wanting to contradict someone because of our impression of them
being senior to us, or more experienced, or more knowledgeable, successful,
etc.
To estimate better, we must build an inclusive culture where the entire
team is invited to participate and to share their opinions. Disagreements
should lead to exploring different viewpoints, which in turn will result in a
better and more analyzed consensus. One way to facilitate this, while
mitigating groupthink and the halo effect, is to use a method first developed
for the Department of Defense known as the "Delphi method",
but which has been adapted for use in software development under the name
"Planning Poker". While often associated with Agile, the
Delphi/Planning Poker approach can be beneficially applied to any estimating
situation.
5. Don't Assume Perfection.
I mentioned this principle in the article PJ's Rules of Project Management, and it is crucial when it comes to estimation. One should be prepared for underestimation due to imperfect knowledge and unanticipated events and discoveries, and expect that not everything will go 100% to plan. In popular practice this is sometimes handled by "padding" the project estimate. It is a form of deception, however, because in the end both the size of the original estimate and the padding amount prove inadequate, keeping companies confused as to why their estimates still aren't working. As such, we'll more thoroughly analyze what this "padding" represents and how to substitute it with a better approach.
I mentioned this principle in the article PJ's Rules of Project Management, and it is crucial when it comes to estimation. One should be prepared for underestimation due to imperfect knowledge and unanticipated events and discoveries, and expect that not everything will go 100% to plan. In popular practice this is sometimes handled by "padding" the project estimate. It is a form of deception, however, because in the end both the size of the original estimate and the padding amount prove inadequate, keeping companies confused as to why their estimates still aren't working. As such, we'll more thoroughly analyze what this "padding" represents and how to substitute it with a better approach.
ESTIMATING: QUICK AND DIRTY
To be clear, I don't recommend estimating "quick and dirty". When
possible, invest the time to do a proper estimate. However, since I know many
will do it anyways, especially under trying deadlines and circumstances, I'll
offer some advice on what I would do.
Triple the base estimate of anything you are doing that is new.
I've seen some project managers knowingly add a 20% padding to an estimate, figuring it a generous allowance for anything unanticipated. I've seen others, who have learned to be more conservative, add up to a 50% padding. In spite of these measures, again and again, projects go over.
I've seen some project managers knowingly add a 20% padding to an estimate, figuring it a generous allowance for anything unanticipated. I've seen others, who have learned to be more conservative, add up to a 50% padding. In spite of these measures, again and again, projects go over.
I'm not sure where this idea came from, but it seems like guesswork to me.
I prefer to use real data as a guide. Having spent over a decade poring over
hours reports on completed projects, I've come to one conclusion; when a task
is underestimated, due to a lack of knowledge or experience, it is usually not
by a factor of 20% or 50%, but by a multiple of 2, 3, 4, or even higher.
I've settled on tripling initial estimates as a good rule of thumb, and I'm
not the only one who has observed this. Alistair Cockburn, one of the pioneers
of the Agile movement, writes that he has found that multiplying estimates by the number pi (3.14) has
an almost magical effect at correcting initial estimates. If the team is well
functioning and the work is well understood, I feel comfortable lowering the
multiplier (down to 2 or 2.5), whereas it's the other way around if the team is
unproven and the work is highly uncertain. In the next section we'll do a more
detailed analysis of why such a large correction is needed. But when pressed
for time, this is my rule of thumb.
Compare the estimate against past project results.
If you've done any projects in the past, you should be using them as a basis of comparison for any future projects. That may sound like an obvious check, but in practice I've found many don't do it, by rationalizing to themselves that "this project" is very different from "the last."
If you've done any projects in the past, you should be using them as a basis of comparison for any future projects. That may sound like an obvious check, but in practice I've found many don't do it, by rationalizing to themselves that "this project" is very different from "the last."
It doesn't matter. You should still be able to answer the following:
- Is the level of effort for
this project bigger or smaller than the last project?
- How long did it take to
complete the last project? How much did it cost us internally?
- If we repeat a similar
performance as we did on the last project, how long will it take us based
on the difference in size and scope?
It's better if you compare the effort to at least two other projects to
average them out. You will be tempted to think that your future performance
will greatly outstrip your historical performance; or that the current
situation will surely have fewer trials than the last; be wary of this.
Instead force yourself to measure and benchmark against past performance. If
your last website project took 8 months, but you now think you can complete a
similarly-sized project in 4 months, you need to seriously reflect on if
planning fallacy is distorting your perception.
It's usually better to range the scope than the time/cost.
A common thought is to give estimates as a range, to express the fact that, after all, it's not an exact science. For example, you might say we estimate the cost will be between $50,000 to $70,000, or that the project will take 6 to 8 weeks to complete.
A common thought is to give estimates as a range, to express the fact that, after all, it's not an exact science. For example, you might say we estimate the cost will be between $50,000 to $70,000, or that the project will take 6 to 8 weeks to complete.
It's a nice idea that often backfires. Here's the problem:
- If the gap between the high
and low end of the range is too much, it will almost certainly be rejected
as an acceptable estimate.
- Whatever the low end of the
range was will somehow become the "de facto" estimate, and
everyone will forget about the high end.
- If you later hit the high
end and point out that it was within the agreed-upon range, somehow people
will be dissatisfied.
What's happening is that people tend to mentally zero-in on the low range
of an estimate, even though it's the statistically most unlikely outcome.
Ranging the estimate this way may work against us. Ranging the scope, however,
gives us better options.
Let's say you have a scope of 12 features. First, get them prioritized, and
and make sure you understand which are "must-haves" and which are
"nice-to-haves". Based on this priority, you can provide options for
the client/stakeholder to choose from, allowing you to scale the estimate in a
variety of ways:
- We can get 9 features
completed by August 1st, or all 12 features completed by September 1st.
- We are confident of
completing 10 features within the estimate, with a chance of complete 1 or
2 additional features.
- We can launch the first 8
features as a Phase 1 and then the second 4 features as a Phase 2.
This puts the focus on what the minimum scope is that can be lived
with--which is better than arguing over how low the time/cost should be.
Itemize assumptions and deadlines.
All estimates are dependent on assumptions and deadlines, and if any change, it's a big deal. It's therefore important to make them transparent and to discuss them regularly.
All estimates are dependent on assumptions and deadlines, and if any change, it's a big deal. It's therefore important to make them transparent and to discuss them regularly.
- Assumptions are an important
aspect of defining the scope, and what is to be expected. This includes
resources, deliverables, and dependencies, all of which have a direct
effect on time and cost. Any misunderstandings or ambiguities are sure to
result in arguments after-the-fact about what the estimate did or didn't
include.
- Every project is contingent
on many internal deadlines, such as turnaround time on reviews and
approvals, when assets are received, when meetings are scheduled, how
quickly requests are fulfilled, and so forth. Many a project has run into
schedule woes because such activities occurred at a more leisurely pace
than hoped for. Its important to not overlook this timing and to get
buy-in on the internal deadlines needed to make the estimate
possible.
If nothing else, I recommend these be documented with every estimate. They
provide something to discuss if the estimate needs to be further negotiated,
and a rationale for revisions should it be necessary.
ESTIMATING: THE PREDICTIVE METHOD
"Waterfall" has a bad rap these days, but most companies still
require detailed project plans before anything can get started; that's a fact
of life. I personally have spent most of my career in this situation. Here's
what I've learned about estimating with this approach:
Find Missing Tasks
Changing requirements is one reason Waterfall estimates run into trouble, however most people are familiar with the process of "change orders" to separate it from the act of estimating (a required practice for this method). The more salient issue is that even the requirements that don'tchange are underestimated.
Changing requirements is one reason Waterfall estimates run into trouble, however most people are familiar with the process of "change orders" to separate it from the act of estimating (a required practice for this method). The more salient issue is that even the requirements that don'tchange are underestimated.
Here's one of the biggest reasons why: missing tasks. When we think about
the activities that must be done, we identify the obvious ones and estimate
those, but miss others. This is why, at the end of the project, there is often
much reflection about tasks that were unnoticed or unanticipated at the start.
Even mundane things are underestimated when we don't think though all the
details. Take a simple task like building a registration form for a website.
How hard can that be, right? Just slap a few text boxes on a page and you're
pretty much done. That's how I use to think. When I discovered later that it
took three times as long to work on a registration form as I thought, I went
back and analyzed where all the time went. What I found is time spent on things
I forgot to consider, such as:
- Form field parameters
- Character limits, default
values, and input masks
- Validation requirements and
messages
- Server side checks for
duplicate usernames
- Minimum password
requirements
- Data and error capture
- Creating database tables
- Reports/exports for
registrations
- Error message if database
cannot be reached
- Error logging if
registration form fails
- Mobile layout/responsive
design
- Response on submit
- Thank you/confirmation page
- Mail account and server
setup for sending confirmation email
- Email copy and subject line
...and so on. You can argue that some of these tasks are "out of
scope" but it's a battle of opinions after the fact, since some were "in
scope" and the others you should've considered beforehand. The point is
that properly breaking things down makes a huge difference in how you estimate.
Think Beyond Coding
Another issue is to think of "coding" as the main activity which you are estimating. How long will the developers take typing away at their keyboards to build this thing? This perspective is likely to result in underestimation.
Another issue is to think of "coding" as the main activity which you are estimating. How long will the developers take typing away at their keyboards to build this thing? This perspective is likely to result in underestimation.
Even those who understand that development is just one part of the
"software development lifecycle" tend to give it the most emphasis.
We think the estimate for the development time, with a little
"padding", should do the trick as a project estimate. My analysis of
actual time spent on projects suggests otherwise.
I submit that, on some projects, only 50% of the time and cost may be spent
on "development tasks", as they are traditionally defined. Sometimes
it's closer to a third of the overall time and cost, or even less. What is
bleeding the rest of the time and the cost on projects? Let's take a look.
The Cost of Executable Requirements
The time and effort needed to get to executable requirements is a classic source of underestimation. By "executable", I mean having enough clarity and detail to the requirements that developers can take the ball and run with it. Many projects suffer from numerous "starts and stops" due to developers not knowing or understanding how to perform tasks due to unclear or incomplete requirements.
The time and effort needed to get to executable requirements is a classic source of underestimation. By "executable", I mean having enough clarity and detail to the requirements that developers can take the ball and run with it. Many projects suffer from numerous "starts and stops" due to developers not knowing or understanding how to perform tasks due to unclear or incomplete requirements.
This translates to wasted time as the team scrambles to find the people who
know the answers to the questions, or who can make the needed decisions.
Meanwhile, development that should've been happening is not happening, and the
estimate gets further and further from reality.
If you're on the "Waterfall" side, it means making sure all the
requirements details are shored up in advance of development, including assets
such as wireframes, data tables, or copy decks, and everything is concretely
defined, including business rules, validation messages, input and output
parameters, and so forth. This amounts to planning for what may be an intense
and lengthy effort.
For this reason many prefer a more "Agile" approach these days,
which takes more of a "just-in-time" approach to requirements, and
generally has requirements definition and development as overlapping, rather
than sequential work phases. Although they are both running at the same time,
keep in mind that it only works if the requirements work stream is running at
least one step ahead of the development work stream, so that
the developers always have something ready to work on. If it is running one
step behind, you waste time with the "start and stop"
issues again.
For more context on requirements, and the effort involved, see A Short Guide to
Writing Software Requirements and How and When to
Write a Requirements Document.
The Cost of Collaboration
You can never completely get rid of problem-solving, research, and trouble-shooting in software development. It's the nature of the job. As such, everyday development is rife with trading emails, conversations in the hallway, brainstorming in front of whiteboards, reviews and meetings both impromptu and scheduled, and so forth. It's part and parcel of "getting things done", but it's a time sink, albeit a necessary one.
You can never completely get rid of problem-solving, research, and trouble-shooting in software development. It's the nature of the job. As such, everyday development is rife with trading emails, conversations in the hallway, brainstorming in front of whiteboards, reviews and meetings both impromptu and scheduled, and so forth. It's part and parcel of "getting things done", but it's a time sink, albeit a necessary one.
If a team of nine people meet for an hour to solve a problem, it's
valuable, but it's still nine man-hours spent on something other than
development. That's the cost of collaboration, as is every
interaction required to get the job done. The more complex a project, the more
collaboration is needed. Be sure to account for the time people need to spend
interacting.
The Cost of Quality
As mentioned earlier, quality means many things, and part of understanding its cost is to take an inventory of what it means for you. For me, it means:
As mentioned earlier, quality means many things, and part of understanding its cost is to take an inventory of what it means for you. For me, it means:
- Architecture Planning
- Unit Test Development
- Writing Test Scripts
- Code Repository and
Continuous Integration Setup
- Development, Staging, and
Production Environment Setup
- Creating Deployment Scripts
- Code Reviews and Design
Patterns
- Knowledge Transfer Sessions
- Error Logging and Messaging
...I could go on, but you get the idea. Each of these is a dedicated effort.
Note that they form a "wrapper" around each development task that can
be as significant of an effort as the development task itself.
If you are doing something novel or custom, you should also factor in time
for:
- Research and Discovery
- Building Prototypes and
Proofs of Concept
- Experimentation
- Troubleshooting
Furthermore, expect it to take repeated effort to reach a
"ready to launch" status. Every project has bugs that need to be
found and fixed, or revisions that will be asked for. It is an iterative
process, with inevitable back-and-forth, and the more time is spent testing
and reviewing things, the more issues may be found to deal with.
Tracking how many rounds of QA are needed or how many revisions are
requested on a project is a fascination of mine. In my experience, requiring
8-10 rounds of QA (or 6-8 weeks) to knock out functional and design issues on a
website launch is not unusual. On content-heavy website launches, I've
recorded 70+ "tickets" of tweaks and revisions. Your mileage will
vary, depending on the type of situation and the stakeholders you're dealing
with (I like to call this variable the "Client Coefficient"). The
QA/UAT process can easily incur the "other 50%" of project time and
cost. Of course, anything you can do to "bake in" quality
throughout the development process or review things in advance will help this
go quicker.
The (Unexpected) Cost of Deployment
A common mistake I see in estimates is assuming a quick and easy deployment, once the project is "done". This is sometimes the case; but other times, I have seen deployments cause an immense amount of last-minute trouble, and right when it's most inconvenient. Chalk it up to "Murphy's Law", but don't think it will never happen to you.
A common mistake I see in estimates is assuming a quick and easy deployment, once the project is "done". This is sometimes the case; but other times, I have seen deployments cause an immense amount of last-minute trouble, and right when it's most inconvenient. Chalk it up to "Murphy's Law", but don't think it will never happen to you.
I've seen occasions when a particular bug or hardware problem related only
to deployment was found right when a project was supposed to go
"live"--and ended up needing days to troubleshoot, submit support
tickets, or find workarounds, holding up projects that were "on
track" up to that point.
Plan ahead by building out a checklist of deployment tasks, assessing each
for risk, and allowing adequate time to perform them. Mitigate the risks by
allocating time to set up staging servers, perform trial runs and put
contingency and monitoring plans in place. In short, the more critical the
deployment, the more thought should be put into its planning and estimation.
Find Risks and Uncertainties
Assessing risk in general is a key part of estimating. Too often we assume "best case scenarios" without stopping to think about the things that might go wrong or cause difficulty. This doesn't mean we have to be pessimistic about everything, just that we should be realistic that some events out of our control are likely to occur, as well as some unanticipated difficulties. We have to be sensitive to when and where those risks are greatest.
Assessing risk in general is a key part of estimating. Too often we assume "best case scenarios" without stopping to think about the things that might go wrong or cause difficulty. This doesn't mean we have to be pessimistic about everything, just that we should be realistic that some events out of our control are likely to occur, as well as some unanticipated difficulties. We have to be sensitive to when and where those risks are greatest.
Here are some potential sources of elevated risk and uncertainty:
- Legacy code. This includes code written by someone other
than your current developers, or any old or deprecated technology which is
still in service. Anywhere a lack of familiarity or currency exists, the
chances of misjudging are high.
- Code with technical
debt. Technical debt
is a serious issue, and every project manager and development team needs
to recognize why and when it is incurred. If you suspect technical debt
has been incurred in the past, remember it alway means extra cost and
effort to pay down or deal with in the future.
- Untried methods. Any time you are trying something new which
you haven't done before, consider the potential for required research,
trial and error, and troubleshooting.
- External dependencies. If you are highly dependent on a third-party
product, service, or vendor, consider the impact of a disruption,
unexpected problem, or discovery that something is not supported. It may
be cause for doing extra due diligence or planning for
contingencies.
- Volatile requirements. If the requirements are subject to change
quickly due to market unpredictability or an influx of new information. If
it must be addressed now instead of later, time for retooling or
refinement may be required.
You will need to analyze the specifics of your own project tasks to
determine additional risks.
Buffer at the Task Level
The estimate for a task should reflect its inherent risk and uncertainty. This can be difficult because we don't know, ahead of time, whether a particular task will go smoothly or not; how do we predict a specific outcome?
The estimate for a task should reflect its inherent risk and uncertainty. This can be difficult because we don't know, ahead of time, whether a particular task will go smoothly or not; how do we predict a specific outcome?
This is where buffering makes sense. In math and science, an analogous
concept is the "confidence interval". It is the degree to to which a
quantitative measurement may vary, generally expressed as a "+/-". In
software development, we focus more on the "+" because our baseline
estimate generally reflects the minimum level of effort needed for a task. It
makes sense to add a reasonable confidence interval to this baseline if we want
to ensure a high probability of falling within the estimate.
You can gauge this buffer based on your experience, or you can use a
formula, such as the 50/90 method. This method has you come up
with two estimates for every task: what you consider to be a
"baseline" estimate (i.e. an estimate you would expect to hit 50% of
the time) and what you consider to be an "outlier" estimate (i.e. an
estimate you would expect to hit 90% of the time, even in the face of some
unexpected difficulties).
Once you have these, the 50/90 method uses a formula (using the concept of
standard deviation and normal distribution) to find a value between these
estimates that is a good in-between, from a probability perspective. Note how
this is superior to simply "padding" an estimate; it
calculates the buffer for each task based on the amount of uncertainty inherent
to that task. Tasks with more uncertainty will naturally have a wider
spread between their 50/90 values and get a bigger buffer vs. predictable tasks
with a smaller spread between their 50/90 values. This is a more empirical and
less arbitrary approach to buffering. To read more about how the 50/90 method
works, I recommend reading Mike Cohn's writeup in his book Agile Estimating and Planning.
Use a Template to Explain the Estimate
I've often seen project managers who supplied an estimate as a total number, or as hours by role, asked to explain themselves to shocked or skeptical stakeholders who don't understand why the estimate is so high.
I've often seen project managers who supplied an estimate as a total number, or as hours by role, asked to explain themselves to shocked or skeptical stakeholders who don't understand why the estimate is so high.
The best way to handle this drama is to avoid it, which you can easily do
if you are transparent with how the estimate was arrived at. The way to do that
is to show an outline of how it all breaks down, particularly any "hidden
tasks" that people may take for granted.
I generally build a template to do just that in either MS Excel or Project.
Below are a few examples using MS Project.
These are fictional projects with fictional tasks, and simplified for the
sake of brevity. However, they illustrate the basic idea. Here is a breakdown
of activities by phases of the "SDLC":

In this next example, I
break down the back-and-forth "revision and review" process inherent
to the typical requirements or design effort. This captures some of the
"cost of collaboration" and is important when the number of
"rounds" it takes matters:

Finally, whenever incremental
variables affect the estimate, I always prefer to itemize them out rather than
batch them together. That's because they represent "variable costs"
and and I don't want them to be misinterpreted as "fixed costs".
If your estimate is contingent on how many website pages you're building,
for example, or how many customers you're supporting, or anything that could be
added to at the last minute, whether intentionally or not, you need a rationale
for why it affects the estimate. Listing things out makes it clearer what the
estimate does and does not include:

The actual estimates for each
line could be in hours, days, or even weeks, that is for you to
decide. The point is that the more you can do to do make your estimate
easy to understand at a glance, the more efficiently you can get through
the presentation and acceptance process.
Deal with "Parkinson's Law" by Delivering More Than Expected
"Parkinson's Law" goes like this: "Work expands to fill the time allotted for its completion." Flipped around, it means if we allow too much time to complete a task, we realize less productivity than was possible. This is a real fear for organizations trying to hit aggressive targets.
"Parkinson's Law" goes like this: "Work expands to fill the time allotted for its completion." Flipped around, it means if we allow too much time to complete a task, we realize less productivity than was possible. This is a real fear for organizations trying to hit aggressive targets.
It contributes to planning fallacy, because it makes us worry about overestimating,
and the potential waste that will occur if we do. The fact is, most of the time
we think we're overestimating, we're actually underestimating;
but in the case that we do, we should turn it into a benefit instead of a
liability.
We can do that by setting "stretch goals" for the estimate that
are not promised, but will be delivered as "extras" if time permits.
In other words, any overestimation should be used to deliver more than
what was expected. This could be in the form of extra features, extra
"polish" to features, or even just launching early. If the
estimate turns out to be adequate only for the original scope then no harm is
done; but if you do manage to perform under the estimate, then consistently
providing additional value is the way to prove to everyone that they need not
worry about Parkinson's Law.
DEFENDING THE PREDICTIVE ESTIMATE
If there's one truism about estimates, it's that someone always wants them
to be lower, and you may feel pressured to do that. Your analysis will be for
nought, however, if you modify your estimate under duress because someone had a
poor reaction to it. To avoid this fate, it is best to be prepared for it in
advance. This means having a plan for when your estimate gets a "no",
as well as understanding how to say "no" to unwise concessions.
To effectively navigate such conversations, you must not take anything
personally. Take it as a rational debate on specific concerns, and nothing
more. Do not fall into the trap of thinking that arguing your side means acting
or coming across as belligerent, unpleasant, or self-centered. It's quite
the opposite. By defending your estimate you are actually proving that you care
about all parties. If you are truly interested in the project being a success,
than defending a good estimate is a sacred trust. Basically you want to do
four things:
1. Establish trust and credibility.
First, you need to convince others that you really are trying to estimate objectively, with the success of the project in mind, and that your method makes sense. Don't feel bad if others imply that you must prove this; it's all part of the game when time and money are at stake.
First, you need to convince others that you really are trying to estimate objectively, with the success of the project in mind, and that your method makes sense. Don't feel bad if others imply that you must prove this; it's all part of the game when time and money are at stake.
This is where all the analysis you've done becomes useful a second time;
just walk everyone through it. When you show everyone exactly how your estimate
breaks down, and explain the rationale behind each part, it will put people at
ease. Just seeing the details and hearing a strong explanation is convincing
enough for most. If there is disagreement in an area, you should discuss
it point by point instead of arguing over the estimate as a whole.
2. Stand for quality and learn to explain it.
A big part of getting on the same page is about agreeing on a quality standard and the level of effort necessary to reach it. What often happens is that stakeholders either haven't considered or don't understand the amount of extra time and work involved to reach the quality level they desire. This can lead to vastly different perceptions of how long something should take.
A big part of getting on the same page is about agreeing on a quality standard and the level of effort necessary to reach it. What often happens is that stakeholders either haven't considered or don't understand the amount of extra time and work involved to reach the quality level they desire. This can lead to vastly different perceptions of how long something should take.
First, be ready to stand for whatever minimum level of quality you feel is
the responsible choice for the project. Second, learn to explain, in clear
terms, what is involved to reach that level of quality so that others
understand. Third, if cuts have to be made that you know will impact quality,
ensure those are communicated, understood, and accepted as a tradeoff.
3. Acknowledge and offer options.
Getting an estimate that was bigger than expected is par for the course. Don't let it stop things from moving forward. The stakeholders want to feel like they are in control of the project, and you take that feeling away if you take an "all or nothing" stance with the estimate. Instead, acknowledge the stakeholder's concerns or constraints, and provide options. Offer them tradeoffs based on scope, assumptions, or deadlines. If things start sounding unreasonable, clarify and review in detail the quality expectations; sometimes that is needed for them to realize it.
Getting an estimate that was bigger than expected is par for the course. Don't let it stop things from moving forward. The stakeholders want to feel like they are in control of the project, and you take that feeling away if you take an "all or nothing" stance with the estimate. Instead, acknowledge the stakeholder's concerns or constraints, and provide options. Offer them tradeoffs based on scope, assumptions, or deadlines. If things start sounding unreasonable, clarify and review in detail the quality expectations; sometimes that is needed for them to realize it.
4. Focus on a shared interest in project success.
What happens if you concede to an estimate that you know in your gut is risky? Remember that planning fallacy occurs even when people think they've made a good estimate. If you know you made a risky estimate, odds are you have really set yourself up for trouble. Let's take an inventory all of the possible consequences; missed deadlines, money problems, broken relationships, burnt out developers, poor quality, unsuccessful product launch, loss of business, loss of reputation, low morale--did I leave anything out?
What happens if you concede to an estimate that you know in your gut is risky? Remember that planning fallacy occurs even when people think they've made a good estimate. If you know you made a risky estimate, odds are you have really set yourself up for trouble. Let's take an inventory all of the possible consequences; missed deadlines, money problems, broken relationships, burnt out developers, poor quality, unsuccessful product launch, loss of business, loss of reputation, low morale--did I leave anything out?
None of that is good for either you or your client or stakeholder.
Therefore your attitude towards estimating should always be about making the
project successful. Once people see that you have their interests in mind, you
can move away from a negotiation mindset to a mindset of collaborative
problem-solving--which is where you wanted to be all along.
I think we can agree these four steps are straightforward. However, since
negotiation skills are usually not taught in companies, it will be incumbent on
you to develop your own skills in this area. For further reading, a good book I
recommend is The Power of a Positive No by William Ury.
ESTIMATING: THE AGILE METHOD
Imagine you are driving a car cross-country to someplace you've never been,
and your speedometer is broken. All you know is that you have to cover 1000
miles to reach your destination, and the only gauge that works reliably on your
car is your trip meter. How can you estimate how long it will take you?
Simple math can help. Check your watch, drive for 100 miles according to
your trip meter, then check your watch again. You now know about how long it
takes to drive 100 miles. Since you have 900 miles left, multiple this time by
9 and you have a decent estimate for the remainder of the trip. To get
more accurate as you go along, take the running average after 200 miles and
apply it to the next 800, and repeat the pattern every 100 miles.
Notice how much easier this is than if we tried to predict our
average speed. We cannot reasonably expect to maintain the same speed
throughout the trip. Instead we have to consider many variables such as:
- The percentage of freeways
vs. interior roads and their various speed limits.
- The occurrence of school
zones, construction zones, and accidents.
- Areas of rush hour traffic.
- Bathroom breaks and stopping
to eat.
...and so on. If we need to give the time of our arrival based on a
predicted speed, it's going to be difficult to guess correctly. On the other
hand, if we take an empirical approach, as we do by measuring our
progress and deriving our speed, we can forecast a more likely
arrival window.
This is the essence of the Agile approach. It seeks to bypass planning
fallacy by focusing on observable results. The key is to measure and quantify
how much work you can get done in a set amount of time. Once you have that
figure, you can build a projection of how long the full project will take. Here
are the high level basics for doing that:
Establish a "Time Box" For Fully Completing an Amount of Work
Popularly called a"sprint", we need a consistent length of time to use as our "divisor" for measuring our productivity. Usually set between 30 days to 2 weeks, the question is not "how much work do we think we can get done" in a sprint, but "how much work did we get done?" in a sprint. This measurement gives us our "working speed", or sprint velocity, which we can use to calculate our "completion window" for the full project.
Popularly called a"sprint", we need a consistent length of time to use as our "divisor" for measuring our productivity. Usually set between 30 days to 2 weeks, the question is not "how much work do we think we can get done" in a sprint, but "how much work did we get done?" in a sprint. This measurement gives us our "working speed", or sprint velocity, which we can use to calculate our "completion window" for the full project.
Note that in order to measure this accurately we need to carefully define
what "done" means. If we base our measurement on work that's
only partially, but not completely done, than we overestimate our true velocity
and its real value becomes hard to determine. The recommendation is that the
work from a sprint should be so complete that it results in working code that
is "ready to deploy".
Make the Requirements Granular and Size It Using User Stories
We need to do more than simply track the "hours" spent working on requirements. We need to determine how much requirements we can get to "done" within the timeframe of our sprint. The key to doing that is to break the requirements into measurable units and to determine how many of those units we can complete each sprint.
We need to do more than simply track the "hours" spent working on requirements. We need to determine how much requirements we can get to "done" within the timeframe of our sprint. The key to doing that is to break the requirements into measurable units and to determine how many of those units we can complete each sprint.
The first step is to make the requirements granular; this can be done by
breaking them into user stories (as described in A Short Guide to
Writing Software Requirements). This way we can measure how many user
stories we are getting done each sprint.
However, user stories are not all the same level of effort; some are bigger
or smaller than others. To compensate for this fact, we need to estimate, not
how long it will take to complete each story, but rather, the relative
size of each story by comparing them to each other.
To be useful for measurement purposes, we need to do it quantitatively. One
technique is to assign each story a rank or score in terms of points, called
"story points". The story points should represent relative scale. In
other words, if a particular user story has a score of "1", then a
story that is twice as big should get a "2", and a story four times
as big should get a "4". Different combinations of stories that add
up to the same number of points should represent similar levels of total
effort. Using a consistent set of story point assignments helps
standardize the estimating process. The most popular method is to use the
"Fibonacci" sequence, which is to use the following set of numbers:
1, 2, 3, 5, 8, 13, 21. Other number sets are possible to use, but it helps if
the gap between points is enough to clearly differentiate levels of effort, yet
not so big that story sizes can be vastly different. Any story greater than 21
points should be subdivided into smaller stories if possible.
When assigning story point values, one should consider the same costs,
risks, and uncertainties we looked at in predictive estimating. If a story has
a fair amount of uncertainty, for example, or will require a lot of testing, or
has a complicated deployment, those are all reasons to bump up its story
points. This is why estimating story points is not just the domain of the
developers, but the responsibility of an entire cross-functional team, which
can assess all the considerations for sizing a story, beyond
just "coding".
Story Points are an Abstraction Layer
Story points are essentially an "abstraction layer" between how we big we think a story is and how long it actually takes. For example, let's say that we think a story will take 100 man-hours. Given the odds of planning fallacy, let's say it actually took us 150 hours to complete, when all is said and done. If you keep estimating each story directly in hours, you are likely to make this error every time.
Story points are essentially an "abstraction layer" between how we big we think a story is and how long it actually takes. For example, let's say that we think a story will take 100 man-hours. Given the odds of planning fallacy, let's say it actually took us 150 hours to complete, when all is said and done. If you keep estimating each story directly in hours, you are likely to make this error every time.
On the other hand, let's say we gave this story 5 story points. We thought
5 story points equaled 100 hours, but it looks like 5 story points really
equals 150 hours. In fact, however, we don't even need to keep track of how
many hours it took. We just need to keep track of how many story points we
actually completed within a sprint. However many story points that
was, it was logically equivalent to however many man-hours we had to spend.
Thus, even though a story point is an approximation, it's useful IF we use
it as a mechanism to mitigate planning fallacy. It is then a matter of
being consistent with our story point estimates, and measuring how many story
points we can complete in a sprint, by adding up the points for all the stories
completed within a sprint. This is our "sprint velocity", which we
can use as a reasonably empirical measurement of how much we can accomplish in
future sprints.
Measure and Calibrate
There are a few things to keep in mind when calculating sprint velocity. First, only completed stories should count towards sprint velocity; giving "partial credit" for "partially completed" stories should be avoided; we are trying to measure how long it takes to "get to done" which means only counting that which made it across the finish line.
There are a few things to keep in mind when calculating sprint velocity. First, only completed stories should count towards sprint velocity; giving "partial credit" for "partially completed" stories should be avoided; we are trying to measure how long it takes to "get to done" which means only counting that which made it across the finish line.
Additionally, we should avoid consistently having incomplete stories
"roll over" from one sprint to the next. That indicates planning
fallacy, because it means we are overcommitting to the amount
of work we think we can complete each sprint.
Rather, our goal is to always complete whatever work we committed to for
the sprint (if any time is left over, we should deliver "extra", just
as with the predictive method); this is the definition of an accurate estimate.
Therefore, once we have determined our sprint velocity, we should use it as a guide
for what we commit to each sprint.
Note that I used the word "commit" because the amount of stories
taken on for a sprint should be a team decision, rather than simply assigned
from "on high". If work is simply assigned, it negates the empirical
method, and usually results in overcommitment. Sprint velocity represents
observable evidence as to how much should be taken on in the next sprint,
unless the team believes there are special circumstances why they may be able
to accommodate more or less work.
In other words, future estimates should be calibrated against past
results. This is the point of measuring and using sprint velocity. With
that being said, realize that it will take some time to "settle" in
on your average sprint velocity.
In the beginning, we don't know what our sprint velocity is, because the
project has no past history. The first few sprints are experimental;
the team picks a number of story points for the sprint that seems reasonable,
then measures how many were actually completed at the end of it; as such don't
expect the first few sprints to be perfect, but take them as learning
experiences for the rest of the project.
It takes some time to dial in estimating story points as well. Eventually,
you want to establish common benchmarks for how big a 3 point or 5 point story
is, for example, by using past stories for comparison. It may take a few
sprints to get there, while the team "fine-tunes" their sizing
assessments. If you stick with it however, the Agile method results in remarkably
reliable predictive ability. The key is that time and cost for a project are
estimated in terms of how many sprints are needed to complete a project. The
length of one sprint becomes the unit of estimate "granularity"
because it is the measurement by which everything is based.
Avoid turning Agile estimating into Predictive estimating
Sprint velocity is a good guide, but keep in mind it's an approximation. As such it may vary from sprint to sprint; it may change over time; and it is affected by context. The great benefit of using it, however, is its likelihood to be more accurate than a purely predictive estimate, because it takes real-world results into account, instead of relying entirely on judgment. This reduces the chances of severe underestimation, as sometimes happens with predictive estimates.
Sprint velocity is a good guide, but keep in mind it's an approximation. As such it may vary from sprint to sprint; it may change over time; and it is affected by context. The great benefit of using it, however, is its likelihood to be more accurate than a purely predictive estimate, because it takes real-world results into account, instead of relying entirely on judgment. This reduces the chances of severe underestimation, as sometimes happens with predictive estimates.
However, if misused, sprint velocity can lead to familiar problems. First,
sprint velocity should never be artificially inflated; this can occur if people
try to make it "look better" by forcing more work into a sprint or by
exaggerating the size of the stories in a sprint. This manipulation works
against its usefulness at preventing planning fallacy, which is the reason for
using it in the first place.
We should also be careful of projecting too far out using current or
historical sprint velocity. This is because the more we assume our sprint
velocity will stay constant over time, the more our estimate becomes predictive instead
of empirical. How do you know your sprint velocity will remain the
same many sprints from now--or even next sprint? The answer is you don't. This
means several things:
- The greater the number of
sprints you project ahead, the more approximate the estimate. Thus, if you
are projecting far ahead to establish a project completion date, it
behooves you to plan conservatively or to define a confidence interval,
such as +/- 1 sprint, to reflect the potential variability in sprint
velocity.
- We should always update our
average sprint velocity as well as our project plan whenever a sprint is
completed, and we have a new velocity measurement to factor in.
- We should treat sprint
velocity as a guide rather than a rule, and temper it with team judgement
when committing to how much work we will take on in a sprint.
To this last point, there are legitimate reasons for a team to decide they
can take on more or less work in a sprint than average sprint velocity would
suggest. Consider just a few ways this can be dynamic:
- Someone may be going on
vacation, reducing the work capacity for the current sprint.
- Coding productivity might
have improved due to a learning experience from the previous sprint,
making the team feel comfortable with taking on additional tasks.
- A change in team composition
occurred, making the team a little more cautious for the current sprint
until they determine the impact of the change.
- A new software tool was
implemented that is helping everyone be a lot more productive, raising
their judgment of how much work they can accomplish.
- Network problems have
recently been hobbling the team with connectivity issues, lowering their
productivity expectations.
...And so on. In other words, while sprint velocity is a good
"baseline", there is always a place to exercise one's judgement on a
case-by-case basis.
Ensure that sprint velocity reflects a "sustainable pace".
One problem is that people interpret the word "sprint" as meaning it should be an "all out race" to get the "maximum amount of work done in the minimum time". This is entirely incorrect, and an unfortunate connotation. Sprint velocity should never be based on a rushed effort, which will inevitably lead to gaps in quality.
One problem is that people interpret the word "sprint" as meaning it should be an "all out race" to get the "maximum amount of work done in the minimum time". This is entirely incorrect, and an unfortunate connotation. Sprint velocity should never be based on a rushed effort, which will inevitably lead to gaps in quality.
Rather, sprint velocity should be based on a "sustainable pace",
which reflects a velocity that:
- The team can sustain
indefinitely without burning out from overwork;
- Includes adequate time to
produce the desired level of quality, including time for quality practices
and quality testing;
- Includes adequate time for
the collaboration necessary to produce a well crafted deliverable.
In other words, the same things we thought about when coming up with a good
predictive estimate also factor into determining a good sprint velocity. If you
are unhappy with the quality of deliverables from a sprint, it may mean you
over-committed to the number of story points you took on. Making an adjustment
to the sprint velocity may make sense, even if means adjusting expectations or
convincing the team to reduce their commitment.
To not do so puts you at risk of the "Bad Agile" situation I
mentioned in What Agile
Software Development Really Means. This is prone to happen if you
rush development to the point that notable bugs or other quality issues exist
with items supposedly "completed" in a sprint. What will happen is
that time on future sprints will need to be spent fixing bugs incurred on prior
sprints, reducing your sprint output. If you let this pattern continue, you
will eventually spend a large part of each sprint cleaning up old issues
instead of working on new stories, effectively killing both your
"Agility" and productivity.
Further Reading
What I've covered here is just the gist of the Agile approach; there are
many more distinctions and concepts to learn, including how to perform sprint
planning, how to "groom" the backlog in preparation of a sprint, when
to break out tasks for user stories, and more. If you're ready to embrace the
Agile approach, two good references to start with are The Scrum Guide by
Ken Schwaber and Jeff Sutherland, and Agile Estimating and Planning by Mike Cohn.
GO MAKE A BETTER WORLD!
In my mind, better estimating is one of the key differences between being a
professional or an amateur in the software development world. But it's about
much, much more than our individual projects or performances. Poor estimates
inevitably result in a poor life experience for everyone, whereas
good estimates have the reverse effect. Here are just a few of the byproducts
of being able to estimate well and being able to hit those estimates:
- A better and more successful
career
- Happier, more satisfied
customers
- A happier and less stressful
work environment
- Team members can afford the
time and energy to do their best work
- A more competitive company
with an enhanced reputation
- More profitable projects